    "headline": "Túnel del Toyo electromechanical equipment installation reaches 40% completion",
    "dek": "Túnel del Toyo road tunnel project has completed 40% of stored electromechanical equipment installation.",
    "prose": "As of 27 November 2026, installation of electromechanical equipment for the Túnel del Toyo tunnel project has reached over 40% completion. [^1]\n\nOfficial government targets schedule the Túnel del Toyo tunnel to enter full operation in October 2027. [^2] The Toyo Tunnel, part of the Nueva Via al Mar Gonzalo Mejia Trujillo project, will be 9.7 kilometers long and one of the longest road tunnels in America. [^3] Invías director Juan Camilo Ostos stated that equipment installation progress was nearly zero 105 days prior to 27 November 2026. [^4]\n\nThe electromechanical equipment had been stored in Bogotá warehouses for months before installation work began. [^5] Governor Andres Julian Rendon of Antioquia highlighted the progress in the installation of ventilators, lighting, and safety equipment in the Toyo Tunnel on 2026-11-26. [^6] The first section of the project, including the main tunnel, has 100% of the civil works completed, while the second section is 80% complete as of September 2026. [^7]\n\nThe Toyo Tunnel will feature 102 ventilators, 22 electrical substations, 358 monitoring cameras, 40 kilometers of fiber optic cable, and fire protection systems. [^8]",
    "cited": "[{\"statement\":\"As of 27 November 2026, installation of electromechanical equipment for the Túnel del Toyo tunnel project has reached over 40% completion.\",\"source\":\"Blu Radio\",\"instrument\":\"News\",\"claim_key\":null,\"published_at\":\"2026-11-27T12:46:56.000Z\",\"publisher_count\":1,\"sources\":[\"Blu Radio\"],\"url\":\"https://www.bluradio.com/regiones/antioquia/tunel-del-toyo-instalacion-de-equipos-electromecanicos-que-estaban-en-bodegas-alcanza-un-40-rg10\"},{\"statement\":\"Official government targets schedule the Túnel del Toyo tunnel to enter full operation in October 2027.\",\"source\":\"Blu Radio\",\"instrument\":\"News\",\"claim_key\":null,\"published_at\":\"2026-11-27T12:46:56.000Z\",\"publisher_count\":1,\"sources\":[\"Blu Radio\"],\"url\":\"https://www.bluradio.com/regiones/antioquia/tunel-del-toyo-instalacion-de-equipos-electromecanicos-que-estaban-en-bodegas-alcanza-un-40-rg10\"},{\"statement\":\"The Toyo Tunnel, part of the Nueva Via al Mar Gonzalo Mejia Trujillo project, will be 9.7 kilometers long and one of the longest road tunnels in America.\",\"source\":\"Valora Analitik\",\"instrument\":\"News\",\"claim_key\":null,\"published_at\":\"2026-11-27T13:00:00.000Z\",\"publisher_count\":1,\"sources\":[\"Valora Analitik\"],\"url\":\"https://www.valoraanalitik.com/tunel-del-toyo-avanza-con-instalacion-de-ventiladores-y-equipos-electromecanicos-en-antioquia/\"},{\"statement\":\"Invías director Juan Camilo Ostos stated that equipment installation progress was nearly zero 105 days prior to 27 November 2026.\",\"source\":\"Blu Radio\",\"instrument\":\"News\",\"claim_key\":null,\"published_at\":\"2026-11-27T12:46:56.000Z\",\"publisher_count\":1,\"sources\":[\"Blu Radio\"],\"url\":\"https://www.bluradio.com/regiones/antioquia/tunel-del-toyo-instalacion-de-equipos-electromecanicos-que-estaban-en-bodegas-alcanza-un-40-rg10\"},{\"statement\":\"The electromechanical equipment had been stored in Bogotá warehouses for months before installation work began.\",\"source\":\"Blu Radio\",\"instrument\":\"News\",\"claim_key\":null,\"published_at\":\"2026-11-27T12:46:56.000Z\",\"publisher_count\":1,\"sources\":[\"Blu Radio\"],\"url\":\"https://www.bluradio.com/regiones/antioquia/tunel-del-toyo-instalacion-de-equipos-electromecanicos-que-estaban-en-bodegas-alcanza-un-40-rg10\"},{\"statement\":\"Governor Andres Julian Rendon of Antioquia highlighted the progress in the installation of ventilators, lighting, and safety equipment in the Toyo Tunnel on 2026-11-26.\",\"source\":\"Valora Analitik\",\"instrument\":\"News\",\"claim_key\":null,\"published_at\":\"2026-11-27T13:00:00.000Z\",\"publisher_count\":1,\"sources\":[\"Valora Analitik\"],\"url\":\"https://www.valoraanalitik.com/tunel-del-toyo-avanza-con-instalacion-de-ventiladores-y-equipos-electromecanicos-en-antioquia/\"},{\"statement\":\"The first section of the project, including the main tunnel, has 100% of the civil works completed, while the second section is 80% complete as of September 2026.\",\"source\":\"Valora Analitik\",\"instrument\":\"News\",\"claim_key\":null,\"published_at\":\"2026-11-27T13:00:00.000Z\",\"publisher_count\":1,\"sources\":[\"Valora Analitik\"],\"url\":\"https://www.valoraanalitik.com/tunel-del-toyo-avanza-con-instalacion-de-ventiladores-y-equipos-electromecanicos-en-antioquia/\"},{\"statement\":\"The Toyo Tunnel will feature 102 ventilators, 22 electrical substations, 358 monitoring cameras, 40 kilometers of fiber optic cable, and fire protection systems.\",\"source\":\"Valora Analitik\",\"instrument\":\"News\",\"claim_key\":null,\"published_at\":\"2026-11-27T13:00:00.000Z\",\"publisher_count\":1,\"sources\":[\"Valora Analitik\"],\"url\":\"https://www.valoraanalitik.com/tunel-del-toyo-avanza-con-instalacion-de-ventiladores-y-equipos-electromecanicos-en-antioquia/\"}]",
    "kind": "news"
  },
  "receipt_verify": "Ed25519 over the dot-joined string `slice_hash.cursor_from.cursor_to.view.view_version.row_count`; public_key and sig are base64url of the raw 32-byte key / 64-byte signature",
  "receipt": {
    "slice_hash": "1b93f8b1c56ca0d27dd5aa43e8f0380a356ad64100d0df13ca5cc7efa4e123e0",
    "cursor_from": "ingest:raw_newsroomfloor.stories:1b93f8b1c56ca0d2",
    "cursor_to": "ingest:raw_newsroomfloor.stories:1b93f8b1c56ca0d2",
    "view": "ingest:raw_newsroomfloor.stories",
    "view_version": "1",
    "row_count": 1,
    "hash_basis": "sha256 over the JSON array of {insertId, json} rows as received (normalized wire shape), computed before the BigQuery forward",
    "credits": 0.01,
    "price_per_100_rows_written": 1,
    "sig": "aFf_jA9cyMm5Luxzi04sjHo824Hz_Dw8tlTbFYcPOvp5HCJDa1B9xtYkkIJQcDT0Rts9a9OejDVL122MA7dGAg",
    "public_key": "bMUigy8O0jOnBxQ4Sc-5lwhIZ8LQVAhxMbR7qESVuUE",
    "signer_path": "lakehouse/data-extract/v1",
    "alg": "Ed25519",
    "signed": true
  },
  "receipt_note": "the ingest door's signed receipt for this revision, verbatim as the door returned it",
  "generation_chain": {
    "wire": {
      "stream": "fountain_news",
      "story_id": "4f2309f6e1e21d8a3d0dea19d8a9c183",
      "thread_id": "81ffd8f15097249e366b966c1548ea0c",
      "thread_label": "Nueva Vía al Mar Gonzalo Mejía Trujillo",
      "novelty": "UPDATE",
      "content_hash": "1ec24118d738822c4d216b912fa51802831b99e2eab1fcafbf822884c83f6384",
      "compose": 3,
      "last_published_at": "2026-11-27T13:00:00.000Z",
      "read_receipt": {
        "slice_hash": "737f0e3d2c91ddc82d9efdee6bfb607b6ce79f52e8986f797833d53d0122cf58",
        "cursor_from": "eyJ0cyI6IjIwMjYtMTEtMjdUMTI6NTQ6MDcuMDAwWiIsImlkIjoiM2ZhMzE1MWQwZjFhNjIxYWM2MjNmYmNiN2UzNzk3ODQiLCJ2IjoiMSJ9",
        "cursor_to": "eyJ0cyI6IjIwMjYtMTEtMjdUMTQ6MzA6NTAuMDAwMDAwWiIsImlkIjoiM2RhZWRhMjEzODAzODBiZGMxNjdkOGNlNDFmZTA1Y2EiLCJ2IjoiMSJ9",
        "view": "v_fountain_news",
        "view_version": "1",
        "row_count": 100,
        "window_days": 3,
        "bytes_scanned": 5191168,
        "credits": 8,
        "price_per_100_rows": 8,
        "sig": "NKf-hf5MjnuCLgJMcAb07Yy7SGkLHwXZ-f8W_JNlUd3sAres1L8NzzFEnmcVb-HHCOVchUb88EoHtVDgNJ1iBw",
        "public_key": "bMUigy8O0jOnBxQ4Sc-5lwhIZ8LQVAhxMbR7qESVuUE",
        "signer_path": "lakehouse/data-extract/v1",
        "alg": "Ed25519",
        "signed": true
      },
      "landing": "air"
    },
    "written_at": "2026-11-27T18:40:54.787Z"
  },
  "cited_facts": [
    {
      "n": 1,
      "statement": "As of 27 November 2026, installation of electromechanical equipment for the Túnel del Toyo tunnel project has reached over 40% completion.",
      "source": "Blu Radio",
      "instrument": "News",
      "claim_key": null,
      "url": "https://www.bluradio.com/regiones/antioquia/tunel-del-toyo-instalacion-de-equipos-electromecanicos-que-estaban-en-bodegas-alcanza-un-40-rg10",
      "occurred_at": null,
      "published_at": null
    },
    {
      "n": 2,
      "statement": "Official government targets schedule the Túnel del Toyo tunnel to enter full operation in October 2027.",
      "source": "Blu Radio",
      "instrument": "News",
      "claim_key": null,
      "url": "https://www.bluradio.com/regiones/antioquia/tunel-del-toyo-instalacion-de-equipos-electromecanicos-que-estaban-en-bodegas-alcanza-un-40-rg10",
      "occurred_at": null,
      "published_at": null
    },
    {
      "n": 3,
      "statement": "The Toyo Tunnel, part of the Nueva Via al Mar Gonzalo Mejia Trujillo project, will be 9.7 kilometers long and one of the longest road tunnels in America.",
      "source": "Valora Analitik",
      "instrument": "News",
      "claim_key": null,
      "url": "https://www.valoraanalitik.com/tunel-del-toyo-avanza-con-instalacion-de-ventiladores-y-equipos-electromecanicos-en-antioquia/",
      "occurred_at": null,
      "published_at": null
    },
    {
      "n": 4,
      "statement": "Invías director Juan Camilo Ostos stated that equipment installation progress was nearly zero 105 days prior to 27 November 2026.",
      "source": "Blu Radio",
      "instrument": "News",
      "claim_key": null,
      "url": "https://www.bluradio.com/regiones/antioquia/tunel-del-toyo-instalacion-de-equipos-electromecanicos-que-estaban-en-bodegas-alcanza-un-40-rg10",
      "occurred_at": null,
      "published_at": null
    },
    {
      "n": 5,
      "statement": "The electromechanical equipment had been stored in Bogotá warehouses for months before installation work began.",
      "source": "Blu Radio",
      "instrument": "News",
      "claim_key": null,
      "url": "https://www.bluradio.com/regiones/antioquia/tunel-del-toyo-instalacion-de-equipos-electromecanicos-que-estaban-en-bodegas-alcanza-un-40-rg10",
      "occurred_at": null,
      "published_at": null
    },
    {
      "n": 6,
      "statement": "Governor Andres Julian Rendon of Antioquia highlighted the progress in the installation of ventilators, lighting, and safety equipment in the Toyo Tunnel on 2026-11-26.",
      "source": "Valora Analitik",
      "instrument": "News",
      "claim_key": null,
      "url": "https://www.valoraanalitik.com/tunel-del-toyo-avanza-con-instalacion-de-ventiladores-y-equipos-electromecanicos-en-antioquia/",
      "occurred_at": null,
      "published_at": null
    },
    {
      "n": 7,
      "statement": "The first section of the project, including the main tunnel, has 100% of the civil works completed, while the second section is 80% complete as of September 2026.",
      "source": "Valora Analitik",
      "instrument": "News",
      "claim_key": null,
      "url": "https://www.valoraanalitik.com/tunel-del-toyo-avanza-con-instalacion-de-ventiladores-y-equipos-electromecanicos-en-antioquia/",
      "occurred_at": null,
      "published_at": null
    },
    {
      "n": 8,
      "statement": "The Toyo Tunnel will feature 102 ventilators, 22 electrical substations, 358 monitoring cameras, 40 kilometers of fiber optic cable, and fire protection systems.",
      "source": "Valora Analitik",
      "instrument": "News",
      "claim_key": null,
      "url": "https://www.valoraanalitik.com/tunel-del-toyo-avanza-con-instalacion-de-ventiladores-y-equipos-electromecanicos-en-antioquia/",
      "occurred_at": null,
      "published_at": null
    }
  ],
  "note": "A signature proves who filed this and that it has not changed since. It never makes a claim true. The dates on cited_facts (occurred_at, published_at) are the forge's, joined at read time; they are not part of the signed basis above."
}